Case No. |
Subject/Name of Parties |
Date of Hearing/Orders |
Status |
|
01 |
Case No. 09 of 2015
Tata Steel Limited
Versus
Jharkhand Renewable Energy Development Agency (JREDA) |
Petition for recognition declaration & approval of Captive Power Plant of TSL as co-generation power plant and waiver/exemption of its RPO |
14.08.2026
at 02.00 P.M |
|
|
02 |
Case No. 09 of 2024
Amalgam Steel & Power Limited (ASPL)
Vrs.
JREDA
|
For seekingdirection that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) from/for the year 2019-20 and 2020-21. |
14.08.2026
at 02.00 P.M |
|
|
03 |
Case No 10 of 2024
Amalgam Steel & Power Limited (ASPL)
Vrs.
JREDA |
For seeking direction that the Captive Power Plant of the petitioner be treated as co-generation power plant and also for relaxation/exemption in compliance of RPO on total installed capacity of 30 MW, since 15 MW out of 30 MW Capacity Generation of Power by Petitioner Company is generated thorugh its waste heat recovery boiler (WHRB) |
14.08.2026
at 02.00 P.M |
|
|
04 |
Case No. 22 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA) |
Exemption in compliance of Renewable Purchase Obligation for the period FY 2020-21 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements |
14.08.2026
at 02.00 P.M |
|
|
05 |
Case No. 23 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA) |
Exemption in compliance of Renewable Purchase Obligation for the period FY 2018-19 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements |
14.08.2026
at 02.00 P.M |
|
|
06 |
Case No. 24 of 2024
M/s ESL Steel Ltd. Vrs. Jharkhand Renewable Energy Development Agency (JREDA) |
Exemption in compliance of Renewable Purchase Obligation for the period FY 2019-20 on the ground that the electricity produced from captive co- generating units of the petitioner is far in excess of its RPO requirements |
14.08.2026
at 02.00 P.M |
|
|
07 |
Case No. 09 of 2025
M/s Tata Steel Limited (TSL)
Vrs.
Jharkhand Renewable Energy Development Ageny (JREDA) |
Exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period 2021-22 |
14.08.2026
at 02.00 P.M |
|
|
08 |
Case No. 10 of 2025
M/s Tata Steel Limited (TSL)
Vrs.
Jharkhand Renewable Energy Development Ageny (JREDA) |
Exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period 2022-23 |
14.08.2026
at 02.00 P.M |
|
|
09 |
Case No. 11 of 2025
M/s Tata Steel Limited (TSL)
Vrs.
Jharkhand Renewable Energy Development Ageny (JREDA) |
Exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period 2023-24 |
14.08.2026
at 02.00 P.M |
|
|
10 |
Case No. 37 of 2025
M/s Usha Martin Limited
Vrs.
Jharkhand Renewable Energy Development Agency (JREDA) |
Petition of M/s Usha Martin Limited under Regualtion 15.2 of JSERC (Renewable Purchase Obligations and its compliance) Regulations, 2016 seeking 4 months extension for RPO compliance at Jamshedpur Plant |
14.08.2026
at 02.00 P.M |
|
|
11 |
Case No. 28 of 2026
Tata Steel Utilties and Infrastructure
Vrs.
Damodar Valley Corporation (DVC) |
Approval of Power Purchase Agreements between Damodar Valley Corporation (DVC) and Tata Steel Utiltites and Service Company Limited (TSUISL) |
14.08.2026
at 02.00 P.M |
|
|
12 |
Case No.32 of 2025
Adhunik Power & Natural Resources Limited |
Petition filed by APNRL Under Section 86(1) (f) of the Electricity Act, 2003 Regarding Dispute on Non-payment of Fixed Chares under PPA |
08.09.2026
at 02.00 P.M |
|
|
13 |
Case No.17 of 2026
Tata Power Company Limited (TPCL) |
Review of order dated 23.03.2026 passed in Case (T) no. 13 of 2025 regarding True-up for FY 2024-25 and Annual Performance Review for FY 2025-26 |
08.09.2026
at 02.00 P.M |
|
|
14 |
Case No.18 of 2026
Tata Power Company Limited (TPCL)
|
Review of order dated 23.03.2026 passed in Case (T) no. 2025 regarding Busniess Plan and MYT petition for Control Period from FY 2026-27 to FY 2030-31. |
08.09.2026
at 02.00 P.M |
|
|
15 |
Suo-Moto Case No.22 of 2026
The Commission on its own motion
Vrs.
Damador Valley Corporation (DVC) & Ors |
Direction given by the Hon'ble APTEL in order dated 24.04.2026 passed in Appeal No. 227 of 2025 & IA No. 1092 of 2025 for identifying DVC's assets forming distribution system within the state of Jharkhand and determine of is tariff with effect from 01.04.2027 |
08.09.2026
at 02.00 P.M |
|
|
16 |
M.P. No 03 of 2026
Damodar Valley Corporation (DVC)
Vrs.
Association of DVC HT Consumers of Jharkhand |
Implementation of the order dated 18.05.2026 passed by Hon'ble APTEL for Electricity in Appeal No. 163 of 2017 |
08.09.2026
at 02.00 P.M |
|
|
17 |
Case No. 43 of 2025
Hindalco Industries Limited
Vrs.
Jharkhand Bijli Vitran Nigam Limited |
For grant of new Electricity Connection for a contracted load of 7500 KVA at supply voltage 132 KVA |
08.09.2026
at 02.00 P.M |
|
|
18 |
Case No.14 of 2026
Adhunik Power & Natural Resources Limited (APNRL)
Vrs.
Jharkhand Urja Vikas Nigam Limited (JUVNL)
Jharkhand Bijli Vitran Nigam Limited (JBVNL) |
Review of order dated 30.03.2026 passed in Case (T) no. 06 of 2025 regarding Truing-up for the FY 2024-25 and Annual Performance Review (APR) of FY 2025-26 |
08.09.2026
at 02.00 P.M |
|
|
19 |
Case No.15 of 2026
Adhunik Power & Natural Resources Limited (APNRL)
Vrs.
Jharkhand Urja Vikas Nigam Limited (JUVNL)
Jharkhand Bijli Vitran Nigam Limited (JBVNL) |
Review of order dated 30.03.2026 passed in Case (T) no. 14 of 2025 regarding approvl of Business Plan, Annual Revenue Requirment and Determination of Tariff for the Control Period starting from 01st April 2026 upto 31st March 2031 |
08.09.2026
at 02.00 P.M |
|
|
20 |
Case No. 11 of 2026
M/s Priya Stone Mines
Vrs.
Jharkhand Bijli Vitran Nigam Limited |
Seeking necessary approval to get fresh electrical connection from Jharkhand Bijli Vitran Nigam Limited on total contract demand 700 KVA applied under H.T.S category at supply voltage of 33 KV |
15.09.2026
at 02.00 P.M |
|
|
21 |
Case No. 07 of 2026
M/s Bharat Coking Coal Ltd., a subsidiary of Coal India Ltd.
Vrs.
Jharkhand Bijli Vitran Nigam Limited and Ors. |
Seeking relaxation of Clause 8.2 with respect to connectivity voltage level for injection of 1.882 MWp Rooftop Solar Power installed at Belgaria Township Phase-I pending development of 33KV infrastructure. |
15.09.2026
at 02.00 P.M |
|
|
22 |
Case No. 22 of 2025
State Load Despatch Center (SLDC) |
Review of order dated 30.04.2025 reg - Provisional of True-up 23-24, Annual Performance Review 2024-25and ARR and SLDC charges for FY 2025-26 |
15.09.2026
at 02.00 P.M |
|
|
23 |
Case (T) No.06 of 2017
Inland Power Limited
Vrs.
Jharkhand Bijli Vitran Nigam Limited
|
(Remanded from Hon'ble APTEL in appeal no. 414 of 2019 & IA No. 449 of 2025) |
15.09.2026
at 02.00 P.M |
|
|
24 |
Case (T) No. 04 of 2018
Inland Power Limited
Vrs.
Jharkhand Bijli Vitran Nigam Limited |
Remanded from the Hon'ble APTEL in appeal no 402 of 2019 & IA No. 450 of 2025 & IA No. 450 of 2025 & IA No. 2061 of 2019 & IA No. 833 of 2020 |
15.09.2026
at 02.00 P.M |
|
|
25 |
Case(T) No.12 of 2019
Inland Power Limited |
Petition in respect of APTEL Order dated 19.03.2024 passed in APL No.125 of 2021 (Arising out of DFR No. 394/2020) for afresh consideration of the issues involved in the impugned Order dated 22.09.2020 passed in Case (Tariff) No. 12/2019 on True-up of FY 2018-19 for 1x63 MW Coal Fired CFBC Thermal Power Project under Section 61 & 62 of the Electricity Act 2003 |
15.09.2026
at 02.00 P.M |
|
|
26 |
Case No. 29 of 2024
M/s Eastern Coalfields Limited
Vrs.
Jharkhand Urja Sancharan Nigam Limited & Ors |
For direction upon the Respondent JUSNL to release the claim amount of Rs.32.97 Cr. which is the 80% of the operations & Maintenance (O&M) cost borned by the petitioner upto April 2015 |
15.09.2026
at 02.00 P.M |
|
|
27 |
Case No.19 of 2025
Jharkhand Renewable Energy Development Agency (JREDA) |
For approval of Capital Expenditure and tariff in respect of Grid Connected MW scale Ground Mounted Solar Power Projects canal-top and floating solar power projects having capacity 2 MW (Project Capacity < 10 MW Category) |
15.09.2026
at 02.00 P.M |
|
|
28 |
Case No.20 of 2025
Jharkhand Renewable Energy Development Agency (JREDA)
Vrs.
Jharkhand Bijli Vitran Nigam Limited (JBVNL) |
Approval of Feed -in Tariff for Ground Mounted, Canal-top and Floating solar projects having capacity less than 10 MW |
15.09.2026
at 02.00 P.M |
|
|
29 |
Misscellaneus Petition No. 01 of 2026
|
For approval of trading of surplus green power by Damodar Valley Corporation |
15.09.2026
at 02.00 P.M |
|
|
30 |
Case No. 21 of 2025
Jharkhand Bijli Vitran Nigam Limited (JBVNL) |
Review of order dated 30.04.2025 regarding True-up for FY 2023-24, Annual Performance Review for FY 2024-25, Aggregate Revenue Requirement & Tariff for FY 2025-26 |
15.09.2026
at 02.00 P.M |
|
|
31 |
Review Case No. 24 of 2026
Inland Power Limited |
Review of order dated 30.03.2026 passed by this Hon'ble Commission in Case (T) No. 15 of 2025 for Business Plan and Multi Year Tariff for Control Period FY 2026-27 to FY 2030-31 for 1x63 MW Coal Fired CFBC Thermal Power Project of Inland Power Limited under Section 61 & 62 of the Electricity Act 2003 |
15.09.2026
at 02.00 P.M |
|
|
32 |
Case No. 01 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority (JREDA) |
For extemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for FY 2020-21. |
29.09.2026
at 02.00 P.M |
|
|
33 |
Case No. 02 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority (JREDA) |
For grant of exemption/relaxation on compliance of Renewable Purchase Obligation considering the fulfillment of RPO compliances are fully met with the electricity produced from Captive Co-generation unit of the petitoiner is for in excess of its RPO requirments for the period of 2024-25 |
29.09.2026
at 02.00 P.M |
|
34 |
Case No. 03 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority (JREDA) |
For grant of exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period of 2025-26. |
29.09.2026
at 02.00 P.M |
|
35 |
Case No. 04 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority (JREDA) |
For grant of exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period of 2021-22 |
29.09.2026
at 02.00 P.M |
|
36 |
Case No. 05 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority (JREDA) |
For grant of exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period of 2022-23 |
29.09.2026
at 02.00 P.M |
|
37 |
Case No. 06 of 2026
M/s Rungta Mines Limited
Vrs.
Jharkhand Renewable Energy Development Authority |
For grant of exemption/relaxation on compliance of Renewable Purchase Obligation considerging the fulfillment of RPO compliance are fully met with the electricity produced from Captive Co-generation unit of the petitoner is for in excess of its RPO requirements for the period of 2023-24. |
29.09.2026
at 02.00 P.M |
|
38 |
Case No. 20 of 2026
Assocation of DVC HT Consumers of Jharkhand |
Review of order dated 15.05.2026 passed in Case (T) No. 01 of 2026 |
29.09.2026
at 02.00 P.M |
|
|
39 |
Case No. 23 of 2026
Damodar Valley Corporation |
Review of order dated 15.05.2026 passed in Case (T) No. 01 of 2026 |
29.09.2026
at 02.00 P.M |
|
|
40 |
26 of 2026
M/s Jain Mangla Iron & Steel Pvt. Ltd. Vrs.
JUVNL & Ors. |
Approval for shifting its voltage supply from 11 KV to 33 KV line under HTS Tariff with an existing contract demand of 650 KVA |
29.09.2026
at 02.00 P.M |
|
|
41 |
Case No. 21 of 2026
M/s Karnpura Rice Mills
Vrs.
Jharkhand Urja Vikas Nigam Limited & Others |
Seeking approval to get fresh electrical connection for supply of power at 33 KV to the petitioner with a contrct demand of 750 KVA |
30.10.2026
at 02.00 P.M |
|
|
42 |
Case No. 12 of 2026
Usha Martin University
Vrs.
Jharkhand Bijli Vitran Nigam Limited & Ors |
Seeking necessary approval to allow it to avial power supply Voltage of 33 KV on its proposed enhanced contract load of 500 KVA under H.T.S category |
Order Reserved |
|
|
43 |
Case No. 13 of 2026
Tata Steel Utilities and Infrastructure Services Limited (TSUISL) with I.A No. 02 of 2026
|
Review of order dated 23.03.2026 passed in Case (T) no.08 of 2025 regarding True-up for FY 2024-25, Annual Performance Review for FY 2025-26 and Aggregate Revenue Requirement & Tariff for FY 2026-27 |
Order Reserved |
|
|
44 |
Case No.16 of 2026
Tata Steel Limited (TSL) with I.A No. 03 of 2026 |
Review of order dated 23.03.2026 passed in Case (T) no.09 of 2025 regarding True-up for FY 2024-25, Annual Performance Review for FY 2025-26 and Aggregate Revenue Requirment & Tariff for FY 2026-27 |
Order Reserved |
|