Subject |
Case No. |
Date |
75. |
Non-providing electric connection to
village-Kuttam, P.O - Chhotamuri, P.S - Sill, Dist - Ranchi. |
13 of 2011 |
26.02.2011 |
74. |
Finalization of the name of
laboratory in which the energy meter of consumers nammely M/s Sukh
Sagar Metal Pvt. Ltd. & M/s Shankar Ferro Alloys Ltd. be tested. |
15 of 2011 |
21.02.2011 |
73. |
Suo motu Proceeding to scrutinize the activity
regarding reducing the T&D loss, Energy auditing and performance of
various generating plants of the licensee - JSEB. |
12 of 2011 |
19.02.2011 |
72. |
An application relating to use of
132 KV Railway owned Transmission line by JSEB for power supply to
Chakradharpur Area by violating the MoU signed by JSEB & Railway and
fixing of wheeling charges for Transmission of power to Chakradharpur
area by JSEB through Railway owned 132 KV Rajkharswan-Chakradharpur
Transmission line. |
06 of 2011 |
19.02.2011 |
71. |
Review and specify the provisions
under Electricity (Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010. |
26 of 2010 |
19.02.2011 |
70. |
An application bringing on record
the illegalities and infirmities committed by the Licensee/Jharkhand
State Electricity Board in allowing interest on security deposit @
3.5% and not @ 6% commencing from 10th June,2003 to the
Domestic/commercial as well as Low Tension Consumers. |
04 of 2011 |
12.02.2011 |
69. |
An application bringing on record
the illegalities committed by the Licensee/Jharkhand State Electricity
Board in charging the energy bill over and above the rates and charges
prescribed in the Tariff Order 2010. |
03 of 2011 |
12.02.2011 |
68. |
An application challenging the
sanction estimate, leving supervision charges @ 21.5% on the
entire/erection of 132 KV Bay and 132 KV D/C Transmission Line
prepared by the Licensee/Jharkhand State Electricity Board. |
01 of 2011 |
12.02.2011 |
67. |
An application for direction upon
Jharkhand State Electricity Board (licensee) to ensure uninterrupted
power supply of electricity with proper voltage in terms of the Power
Supply Agreement entered into between the parties. |
29 of 2010 |
12.02.2011 |
66. |
Suo motu Proceeding to scrutinize the activity
regarding reducing the T&D loss, Energy auditing and performance of
various generating plants of the licensee - JSEB. |
12 of 2011 |
12.02.2011 |
65. |
Non-providing electric connection to
village-Kuttam, P.O - Chhotamuri, P.S - Sill, Dist - Ranchi. |
13 of 2011 |
10.02.2011 |
64. |
Tariff filing of JSEB. |
33 of 2010 |
10.02.2011 |
63. |
Non-providing Electric Connection to Villagers
of Baram (Dipatoli), Mahilong, Namkom, Ranchi. |
11 of 2010 |
09.02.2011 |
62. |
Suo Motu Proceeding to scrutinize the activity
regarding reducing the T&D loss, Energy auditing and performance of
various generating plants of the licensee - JSEB. |
12 of 2011 |
09.02.2011 |
61. |
An application for direction upon
Jharkhand State Electricity Board (licensee) to ensure uninterrupted
power supply of electricity with proper voltage in terms of the Power
Supply Agreement entered into between the parties. |
29 of 2010 |
22.01.2011 |
60. |
An application bringing on record
the illegalities and infirmities committed by the Licensee/Jharkhand
State Electricity Board in allowing interest on security deposit @
3.5% and not @ 6% commencing from 10th June,2003 to the
Domestic/commercial as well as Low Tension Consumers. |
04 of 2010 |
22.01.2011 |
59. |
An application bringing on record
the illegalities committed by the Licensee/Jharkhand State Electricity
Board in charging the energy bill over and above the rates and charges
prescribed in the Tariff Order 2010. |
03 of 2011 |
22.01.2011 |
58. |
An application challenging the
sanction estimate, leving supervision charges @ 21.5% on the
entire/erection of 132 KV Bay and 132 KV D/C Transmission Line
prepared by the Licensee/Jharkhand State Electricity Board. |
01 of 2011 |
22.01.2011 |
57. |
Review and specify the provisions
under Electricity (Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010. |
26 of 2010 |
22.01.2011 |
56. |
Filing of Tariff Petitions for FY 2011-12. |
30 of 2010 |
12.01.2011 |
55. |
Non-providing electric connection
|
32 of 2010 |
10.01.2011 |
54. |
Filing of Tariff Petitions for FY 2011-12. |
30 of 2010 |
04.01.2011 |
53. |
Introduction of spot billing
by JSEB. |
31 of 2010 |
14.12.2010 |
52. |
Filing of Tariff Petitions for FY 2011-12. |
30 of 2010 |
04.12.2010 |
51. |
An application for direction upon
Jharkhand State Electricity Board (licensee) to ensure uninterrupted
power supply of electricity with proper voltage in terms of the Power
Supply Agreement entered into between the parties. |
29 of 2010 |
18.12.2010 |
51. |
An application challenging the
action of respondent-JSEB in providing the electrical connection to
the unauthorized/legal occupants in the township of Fertilizers
Corporation of India Ltd., Sindri without following the provision of
clause 5.3 (b) of JSERC (Electricity Supply Code) Regulation, 2005. |
27 of
2010 |
18.12.2010 |
50 |
Review and specify the provisions
under Electricity (Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010. |
26 of 2010 |
18.12.2010 |
49. |
An application challenging the
action of respondent-JSEB in providing the electrical connection to
the unauthorized/legal occupants in the township of Fertilizers
Corporation of India Ltd., Sindri without following the provision of
clause 5.3 (b) of JSERC (Electricity Supply Code) Regulation, 2005. |
27 of
2010 |
04.12.2010 |
48. |
Review and specify the provisions
under Electricity (Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010 |
26 of
2010 |
04.12.2010 |
47. |
Show- Cause Notice
for Non-providing of electrical connection to the residents of
village. |
16 of
2008 |
04.12.2010 |
46. |
Review and specify the provisions
under Electricity Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010. |
26 of
2010 |
20.11.2010 |
45. |
Show- Cause Notice
for Non-providing of electrical connection to the residents of
village. |
16 of
2010 |
09.11.2010 |
44. |
Review and specify the provisions
under Electricity Supply Code Amendment) Regulations,2010 as gazetted
and notified on 01.09.2010. |
26 of
2010 |
09.11.2010 |
43. |
An application challenging the
action of respondent-JSEB in providing the electrical connection to
the unauthorized/legal occupants in the township of Fertilizers
Corporation of India Ltd., Sindri without following the provision of
clause 5.3 (b) of JSERC (Electricity Supply Code) Regulation, 2005. |
27 of
2010 |
30.10.2010 |
42. |
An application for
concurrence of the State Load Dispatch Center under Regulation 8(1) of
the Central Electricity Regulatory Commission Open Access Regulations,
2008 read with clause 3.1 of the Short Term Open Access Inter-State
Transmission (Bilateral Transaction) Procedure for scheduling.
|
22 of
2010 |
26.10.2010 |
41. |
An application for
concurrence of the State Load Dispatch Center under Regulation 8(1) of
the Central Electricity Regulatory Commission Open Access Regulations,
2008 read with clause 3.1 of the Short Term Open Access Inter-State
Transmission (Bilateral Transaction) Procedure for scheduling.
|
22 of
2010 |
25.10.2010 |
40. |
Petition for review of
order on petition for determination of ARR and Tariff Proposal for
2010-11 of JUSCO. |
24 of
2010 |
23.10.2010 |
39. |
Petition for Review of order in case no 05 of
2010. |
20 of
2010 |
23.10.2010 |
38. |
An application for
concurrence of the State Load Dispatch Center under Regulation 8(1) of
the Central Electricity Regulatory Commission Open Access Regulations,
2008 read with clause 3.1 of the Short Term Open Access Inter-State
Transmission (Bilateral Transaction) Procedure for scheduling.
|
22 of
2010 |
12.10.2010 |
37. |
Order on Show-cause of JSEB for replacement
Replacement of existing meters by digital meters at the cost of the
consumers. |
25 of
2010 |
11.10.2010 |
36. |
An application for
concurrence of the State Load Dispatch Center under Regulation 8(1) of
the Central Electricity Regulatory Commission Open Access Regulations,
2008 read with clause 3.1 of the Short Term Open Access Inter-State
Transmission (Bilateral Transaction) Procedure for scheduling.
|
22 of
2010 |
09.10.2010 |
35. |
Petition for review of
order on petition for determination of ARR and Tariff Proposal for
2010-11 of JUSCO. |
24 of
2010 |
09.10.2010 |
34. |
Petition for Review of order in case no 05 of
2010. |
20 of
2010 |
09.10.2010 |
33. |
An application for
quashing and restraining the respondents- JSEB from taking Security
Amount or any other charges without any permission from this Hon'ble
Commission. |
23 of
2010 |
30.09.2010 |
32. |
An application for
concurrence of the State Load Dispatch Center under Regulation 8(1) of
the Central Electricity Regulatory Commission Open Access Regulations,
2008 read with clause 3.1 of the Short Term Open Access Inter-State
Transmission (Bilateral Transaction) Procedure for scheduling.
|
22 of
2010 |
30.09.2010 |
31. |
An
application for a direction to the JSEB to restrain from taking the
security amount at the enhanced rate as published in local Daily news
paper Hindustan dt.06.07.2010 & also for a direction to the
respondents not to charge the security deposit without the permission
of this Hon'ble Commission also not to charge from the existing
consumers on the load for which the security amount had already been
deposited much earlier at the time of taking new connection. |
21 of
2010 |
30.09.2010 |
30. |
Petition for Review of order in case no 05 of
2010. |
20 of
2010 |
04.09.2010 |
29. |
Clarification of
Tariff Order 2003-04 & 2010-11 in relation to HTS Consumers. |
18 of
2010 |
21.08.2010 |
28. |
An application under
Section 86 (i) (f) of the Electricity Act, 2003 for a direction to
Respondent -Jharkhand State Electricity Board to sign the Power
Purchase Agreement (PPA) between the Petitioner -BHPC and
Respondent -JSEB in respect of sale of power to JSEB from different
Hydro Electric Projects located in State of Jharkhand. |
06 of
2010 |
21.08.2010 |
27. |
An application under
Section 86 (i) (f) of the Electricity Act, 2003 for a direction to
Respondent -Jharkhand State Electricity Board to sign the Power
Purchase Agreement (PPA) between the Petitioner -BHPC and
Respondent -JSEB in respect of sale of power to JSEB from different
Hydro Electric Projects located in State of Jharkhand. |
06 of 2010 |
26.06.2010 |
26. |
An Application U/s 76
of the Electricity Act, 2003. |
10 of
2010 |
12.06.2010 |
25. |
Petition for Seeking
Permission for issue of power connection to Water treatment plant of
PHED (Govt. of Jharkhand), Near Old Purulia Road, Mango and Intake
Well Plant, Kunwar Basti, Mango, PHED, Government of Jharkhand, both
are outside the licensed area. |
07 of
2010 |
11.05.2010 |
24. |
An application under
Section 86 (i) (f) of the Electricity Act, 2003 for a direction to
Respondent -Jharkhand State Electricity Board to sign the Power
Purchase Agreement (PPA) between the Petitioner -BHPC and
Respondent -JSEB in respect of sale of power to JSEB from different
Hydro Electric Projects located in State of Jharkhand. |
06 of 2010 |
08.05.2010 |
23. |
An application under
Section 86 (i) (f) of the Electricity Act, 2003 for a direction to
Respondent -Jharkhand State Electricity Board to sign the Power
Purchase Agreement (PPA) between the Petitioner -BHPC and
Respondent -JSEB in respect of sale of power to JSEB from different
Hydro Electric Projects located in State of Jharkhand. |
06 of 2010 |
17.04.2010 |
22. |
Petition for
a direction upon the Jharkhand State Electricity Board (SLDC) to
facilitate the petitioner in order to grant short term open access
permission for sale of power on Power Exchange. |
02 of 2010 |
25.02.2010 |
21. |
Order on show-cause of
JSEB for fixation of Tariff. |
01 of 2010 |
20.02.2010 |
20. |
Order on show-cause of
JSEB for fixation of Tariff. |
01 of 2010 |
15.02.2010 |
19. |
Order on show-cause of
JSEB for fixation of Tariff. |
01 of 2010 |
29.01.2010 |
18. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
09.01.2010 |
2009 |
17. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
05.12.2009 |
16. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
14.11.2009 |
15. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
31.10.2009 |
14. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
15.10.2009 |
13. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003.
|
17 of 2009 |
03.10.2009 |
12. |
An application for determination of
Distribution and Retail Tariff and for interim/provisional
tariff of Damodar Valley Corporation.
|
16 of 2009 |
03.10.2009 |
11. |
Petition for Right to OPEN ACCESS as provided
under section 9(2) of Electricity Act 2003. |
17 of 2009 |
15.09.2009 |
10. |
An application for determination of
Distribution and Retail Tariff and for interim/provisional
tariff of Damodar Valley Corporation. |
16 of 2009 |
14.09.2009 |
09. |
An application for determination of
Distribution and Retail Tariff and for interim/provisional
tariff of Damodar Valley Corporation. |
16 of 2009 |
11.09.2009 |
08. |
An application for
a declaration that the agreement executed between the petitioner and
the respondent - JSEB is in conflict with the Tariff Order 2003-04
and for a clarification to the effect that the load of consumer's
induction furnace cannot be determined by the respondent -JSEB on the
basis of source power, which is inconsistent with the Tariff Order
2003-04.
|
03 of 2009 |
11.09.2009 |
07. |
An application for modification of
order dated 07.02.2006 Passed by the Commission by which the
Commission did not allow the petitioner -JSEB to collect additional
security from its consumers.
|
07 of 2009 |
05.09.2009 |
06. |
An application for modification of
order dated 07.02.2006 Passed by the Commission by which the
Commission did not allow the petitioner -JSEB to collect additional
security from its consumers.
|
07 of 2009 |
22.08.2009 |
05. |
An application for
a declaration that the agreement executed between the petitioner and
the respondent - JSEB is in conflict with the Tariff Order 2003-04
and for a clarification to the effect that the load of consumer's
induction furnace cannot be determined by the respondent -JSEB on the
basis of source power, which is inconsistent with the Tariff Order
2003-04.
|
03 of 2009 |
13.08.2009 |
04. |
An application for modification of
order dated 07.02.2006 Passed by the Commission by which the
Commission did not allow the petitioner -JSEB to collect additional
security from its consumers.
|
07 of 2009 |
08.08.2009 |
03. |
An application for modification of
order dated 07.02.2006 Passed by the Commission by which the
Commission did not allow the petitioner -JSEB to collect additional
security from its consumers.
|
07 of 2009 |
01.08.2009 |
02. |
Regarding Fuel Cost Surcharge. |
08 of
2009 |
06.07.2009 |
01. |
An application for modification of
order dated 07.02.2006 Passed by the Commission by which the
Commission did not allow the petitioner -JSEB to collect additional
security from its consumers.
|
07 of
2009 |
04.07.2009 |